CIL charge on projects abandoned mid-way
phoebe martin, modified 4 Years ago.
CIL charge on projects abandoned mid-way
New Member Posts: 5 Join Date: 31/08/18 Recent Posts
0
When circumstances cause a small scale developer to abandon a project after commencement what are your practices for procuring the due CIL charge?
In the past when a proposal has been halted mid-way through a new application has been required and we charge CIL on that instead. However, if the new app was refused and no further proposals were submitted by the developer what do we have in terms of CIL regs to back up us in pursuing the CIL charge? We must also consider whether chasing the payment is appropriate, for example if they are never going to (and cannot lawfully) continue with the original permission. Has anyone had a similar situation and can advise?