<?xml version="1.0" encoding="UTF-8"?>
<feed xmlns="http://www.w3.org/2005/Atom" xmlns:dc="http://purl.org/dc/elements/1.1/">
  <title>Phased Development and CIL Implications</title>
  <link rel="self" href="https://khub.net/c/message_boards/find_thread?p_l_id=53683759&amp;threadId=1161627329" />
  <subtitle>Phased Development and CIL Implications</subtitle>
  <id>https://khub.net/c/message_boards/find_thread?p_l_id=53683759&amp;threadId=1161627329</id>
  <updated>2026-07-16T20:21:58Z</updated>
  <dc:date>2026-07-16T20:21:58Z</dc:date>
  <entry>
    <title>RE: Phased Development and CIL Implications</title>
    <link rel="alternate" href="https://khub.net/c/message_boards/find_message?p_l_id=53683759&amp;messageId=1165928205" />
    <author>
      <name>Debbie Wilson</name>
    </author>
    <id>https://khub.net/c/message_boards/find_message?p_l_id=53683759&amp;messageId=1165928205</id>
    <updated>2025-03-10T08:13:49Z</updated>
    <published>2025-03-10T08:13:49Z</published>
    <summary type="html">&lt;p&gt;Thank you Robyn and Ahsan, very useful information.&lt;/p&gt;</summary>
    <dc:creator>Debbie Wilson</dc:creator>
    <dc:date>2025-03-10T08:13:49Z</dc:date>
  </entry>
  <entry>
    <title>RE: Phased Development and CIL Implications</title>
    <link rel="alternate" href="https://khub.net/c/message_boards/find_message?p_l_id=53683759&amp;messageId=1162785602" />
    <author>
      <name>Ahsan Ghafoor</name>
    </author>
    <id>https://khub.net/c/message_boards/find_message?p_l_id=53683759&amp;messageId=1162785602</id>
    <updated>2025-03-03T11:37:45Z</updated>
    <published>2025-03-03T11:37:45Z</published>
    <summary type="html">&lt;p style="margin-bottom:11px"&gt;&lt;span style="font-size:11pt"&gt;&lt;span style="line-height:107%"&gt;&lt;span style="font-family:Aptos,sans-serif"&gt;Agree this isn't straightforward scenario and should be tackled in a step-by-step approach. &lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px"&gt;&lt;span style="font-size:11pt"&gt;&lt;span style="line-height:107%"&gt;&lt;span style="font-family:Aptos,sans-serif"&gt;It seems the developer is looking for a work-around liability to pay CIL. &lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px"&gt;&lt;span style="font-size:11pt"&gt;&lt;span style="line-height:107%"&gt;&lt;span style="font-family:Aptos,sans-serif"&gt;First step is to decide if a NMA application can be used to&amp;nbsp;amend the operative part/description of the original PP. It seems the developer wants to make the original retrospective PP into phased PP so it grants PP for a phased development of 3 stages. I think there are likely to be fundamental differences between the terms of the retrospective PP and the amended phased proposal. &lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px"&gt;&lt;span style="font-size:11pt"&gt;&lt;span style="line-height:107%"&gt;&lt;span style="font-family:Aptos,sans-serif"&gt;The courts have consistently held that the operative part of the original PP cannot be amended via NMA or s73 route; the former is for non-material amendments to a scheme while the latter is only used to vary conditions.&amp;nbsp;It seems the retrospective PP regularises the demolition&amp;nbsp;of the original dwelling and its replacement with a new dwelling, which is different in substance to a phased development. Perhaps your planning colleagues should consider the recent CoA judgment in Fiske v Test Valley before determining the new applications.&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px"&gt;&lt;span style="font-size:11pt"&gt;&lt;span style="line-height:107%"&gt;&lt;span style="font-family:Aptos,sans-serif"&gt;For CIL purposes, OVAL v BANES also makes clear that the decision whether a development is going to be phased needs to be made not just before the commencement of the development but before the planning application. It also indicates that&amp;nbsp;reserving a discretion to phase or not phase will be insufficient; if the intention to phase arises subsequent to grant then action must be taken before the commencement of the development - it's too late once the s73A PP has been implemented through demolition (remember for CIL the date of grant of PP is the commencement date). &lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px"&gt;&lt;span style="font-size:11pt"&gt;&lt;span style="line-height:107%"&gt;&lt;span style="font-family:Aptos,sans-serif"&gt;There is a possibility of applying under section 73 to vary conditions imposed on the original retrospective PP. Presumably, there is a plans condition which the developer may wish to vary thus introduce&amp;nbsp;a phased plan. However, Reg 2(1) defines a "phased planning permission" which expressly provides for development to be carried out in phases: again, you need to take a view as to whether s73 application can be used to vary a retrospective PP as the development has already commenced.&amp;nbsp;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&lt;span style="font-size: 1rem;"&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&amp;nbsp;&lt;/p&gt;</summary>
    <dc:creator>Ahsan Ghafoor</dc:creator>
    <dc:date>2025-03-03T11:37:45Z</dc:date>
  </entry>
  <entry>
    <title>RE: Phased Development and CIL Implications</title>
    <link rel="alternate" href="https://khub.net/c/message_boards/find_message?p_l_id=53683759&amp;messageId=1161698818" />
    <author>
      <name>Robyn Walkey</name>
    </author>
    <id>https://khub.net/c/message_boards/find_message?p_l_id=53683759&amp;messageId=1161698818</id>
    <updated>2025-02-28T16:00:25Z</updated>
    <published>2025-02-28T16:00:25Z</published>
    <summary type="html">&lt;p&gt;Hi Debbie,&lt;/p&gt;

&lt;p&gt;That is a confusing one!&lt;/p&gt;

&lt;p&gt;In my opinion, as soon as the retrospective planning permission was granted then the CIL became payable, and any subsequent NMAs or S73As wouldn't change that. I'm basing this mainly on the Oval v BANES case (although that wasn't retrospective when the original application was granted), where the inspector says as that the planning permission at the time wasn't phased then the CIL was payable from the original payment date. In Gardiner v Hertsmere, the judge's reasons for not allowing the retrospective exemption include:&amp;nbsp;"&lt;em&gt;The references to ‘intends’ and ‘commission’ are forward looking. They are not consistent with an application by a person who has already built or begun to build a dwelling."&amp;nbsp;&lt;/em&gt;&lt;/p&gt;

&lt;p&gt;It is difficult, as I think for a prospective application an NMA &amp;amp; S73 would potentially be acceptable to add phasing&amp;nbsp;to a permission, but I don't think there's been a retrospective one tested.&amp;nbsp;I wonder&amp;nbsp;whether&amp;nbsp;your planning officers are likely to grant the subsequent applications, if they don't add anything in planning terms.&lt;/p&gt;

&lt;p&gt;Sorry, this isn't particularly useful, we haven't come across one like this yet! I can see the arguable points as in a phased development each phase is a separate chargeable development, so theoretically they would have time to submit a SBE claim, but it doesn't feel like an intention of the regs imo.&lt;/p&gt;

&lt;p&gt;Robyn&lt;/p&gt;</summary>
    <dc:creator>Robyn Walkey</dc:creator>
    <dc:date>2025-02-28T16:00:25Z</dc:date>
  </entry>
  <entry>
    <title>Phased Development and CIL Implications</title>
    <link rel="alternate" href="https://khub.net/c/message_boards/find_message?p_l_id=53683759&amp;messageId=1161627328" />
    <author>
      <name>Debbie Wilson</name>
    </author>
    <id>https://khub.net/c/message_boards/find_message?p_l_id=53683759&amp;messageId=1161627328</id>
    <updated>2025-02-28T13:28:25Z</updated>
    <published>2025-02-28T13:28:25Z</published>
    <summary type="html">&lt;p&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;Hi all,&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;Please could you let me know if you have come across the following or can you provide advice of any kind:&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;We have a scenario where planning permission has been granted for extension works, but the dwelling has been demolished resulting in a retrospective permission being granted for the new dwelling.&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;We've now received 2 further applications for this site, the first a non material amendment to amend the description to a phased development of 3 stages and a S73 to include the phasing. If these are validated we will not be removing the word 'retrospective' because the development is retro.&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;Phase 1 would be demolition (because 1 and a half walls of the original dwelling are still in situ -just about!), phase 2 would be groundworks and phase 3&amp;nbsp;would be construction of a new dwelling.&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;However, could this mean that the CIL would no longer be due because these permissions (if permitted) would supersede the retrospective permission because:&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;Reg 9. states.&amp;nbsp;&amp;nbsp;&lt;b&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;9.&lt;/span&gt;&lt;/span&gt;&lt;/b&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;— (1) The chargeable development is the development for which planning permission is granted.&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;and Reg 7 states&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-top:7px; margin-bottom:11px; margin-left:28px; text-indent:-21.3pt"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;b&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;7.&lt;/span&gt;&lt;/span&gt;&lt;/b&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;— (1) This regulation has effect for determining when development is to be treated as commencing for the purposes of Part 11 of PA 2008.&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-top:7px; margin-bottom:11px; margin-left:28px"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;(2) Development is to be treated as commencing on the earliest date on which any material operation begins to be carried out on the relevant land.&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px; text-indent:21.3pt"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;(3) Paragraph (2) is subject to the following provisions of this regulation.&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-top:7px; margin-bottom:11px; margin-left:28px"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;(4) Development is to be treated as commencing on the day planning permission is granted for that development if planning permission had previously been granted for that development for a limited period.&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px; text-indent:21.3pt"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;(5) Development for which planning permission is—&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px; text-indent:36.0pt"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;strong&gt;&lt;u&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="background:yellow"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;(a) granted under section 73A of TCPA (planning permission for development already&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/u&gt;&lt;/strong&gt;&lt;span style="background:yellow"&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px; text-indent:36.0pt"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;strong&gt;&lt;u&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="background:yellow"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;carried out); or&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/u&gt;&lt;/strong&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-top:7px; margin-bottom:11px; margin-left:48px"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;(b) granted or modified under section 177(1) of TCPA 1990 (grant or modification of&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-bottom:11px; text-indent:36.0pt"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;planning permission on appeals against enforcement notices),&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-top:7px; margin-bottom:11px; margin-left:28px"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;&lt;strong&gt;&lt;u&gt;&lt;span style="font-size:11.0pt"&gt;&lt;span style="background:yellow"&gt;&lt;span style="font-family:&amp;quot;Calibri&amp;quot;,sans-serif"&gt;is to be treated as commencing on the day planning permission for that development is granted or modified (as the case may be).&lt;/span&gt;&lt;/span&gt;&lt;/span&gt;&lt;/u&gt;&lt;/strong&gt;&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-top:7px; margin-bottom:11px; margin-left:28px"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;Therefore, does this mean that with the latest permission the applicants could submit their relief forms because works has not commenced under the new permission? If so, this is a loophole and why has it not been tried before?&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;

&lt;p style="margin-top:7px; margin-bottom:11px; margin-left:28px"&gt;&lt;span style="font-size:12pt"&gt;&lt;span style="font-family:&amp;quot;Times New Roman&amp;quot;,serif"&gt;I hope the above makes sense and any advice would be much appreciated.&lt;/span&gt;&lt;/span&gt;&lt;/p&gt;</summary>
    <dc:creator>Debbie Wilson</dc:creator>
    <dc:date>2025-02-28T13:28:25Z</dc:date>
  </entry>