Charging CIL for works without planning permissionCharging CIL for works without planning permissionhttps://khub.net/c/message_boards/find_thread?p_l_id=53683759&threadId=5306832392024-03-29T05:34:29Z2024-03-29T05:34:29ZCharging CIL for works without planning permissionDebbie Wilsonhttps://khub.net/c/message_boards/find_message?p_l_id=53683759&messageId=5306832382021-09-23T15:30:01Z2021-09-23T15:02:16Z<p>Hi,</p>
<p>I have a scenario where planning permission has been granted for a
CIL liable development of which the levy has been paid. However,
planning enforcement have been out on site and have discovered that
since payment of CIL building works have continued, but not to the
submitted plans. The building (block of flats) is now larger in size
which means CIL is due for the additional GIA.</p>
<p>The applicants have been informed that a new planning application has
to be submitted to regularise the additional works that have taken
place but they do not want to do this.</p>
<p>Our enforcement team are considering issuing an enforcement notice,
if the applicant went to appeal and lost we would be able to insist on
the planning application, however, if enforcement action isn't taken
and a new planning application isn't submitted is there anything I can
do re trying to get the levy paid for the additional GIA?</p>Debbie Wilson2021-09-23T15:02:16Z