Development abandoned
carmel huntley, modifié il y a 1 année.
Development abandoned
New Member Publications: 16 Date d'inscription: 21/05/20 Publications Récentes
0
Hi all,
Just looking for any advice please or an approach taken if you have dealt with a similar case .....we have a case where the pp was to demolish 2 houses and build flats. The houses have been demolished so effectively works have 'commenced' and CIL should be paid. However, due to a land ownership issue the developer has pulled away from the site completely and the build will not be going ahead. Should we still charge the CIL-£80k? Legislation and case law suggests it should still be paid but it feels a bit harsh.....any help would be much appreciated. Thanks, Carmel